Wednesday, 19th July.
A day of great progress, above and below ground, indoors and outside!
Benoit and friend arrived promptly at 08.00 – as did the new Fosse on the back
of a lorry. By 08.19 it was in place and
the lorry gone!
So the rest of the day was spent firstly
finding then breaking into and extending the sewer pipe – along with jocular
instructions as to when we could and could not use the system.
At some point, Daniel the surveyor arrived and duly signed everything
off so that the entire installation now just awaits multiple lorry-loads of
infill tomorrow.
Below ground indoors, similar progress.
Ali came to help with marking out the gores for Castor – I’m never to be relied
on for measuring – and then I cut them (my hands are tired tonight, it was all
knife-work!) and we transferred the measurement both to the other section and
to the remaining sections for Pollux.
At the end of which I bonded both sections – and their corresponding bow fairings – together. I would have done more but I cannot find any jig-saw blades.
Perhaps best; a good supper of Pad Thai (from a kit) and stir-fried bean-sprouts. Delicious.